Domain 7/7.9 Understand and participate in change management processes
A zero-day in a hospital's VPN gateway is being actively exploited, and the vendor has released an emergency patch. The CAB does not meet until next week. Leopoldo, the IT operations manager, decides. What is the BEST course of action?
- APatch now; tell the CAB later
- BWait for the scheduled CAB
- CEmergency change process
- DShut the VPN until fully tested
Show the answer
Correct answer: C. Emergency changes are fast but still controlled.
- A. Incorrect. Bypassing change control skips approval and rollback planning.
- B. Incorrect. Waiting leaves an exploited flaw open for a week.
- C. Correct. Expedited approval keeps control and traceability while closing the exposure quickly.
- D. Incorrect. A long shutdown disrupts the business unnecessarily.