Domain 7/7.12 Test Disaster Recovery Plan (DRP)
A regional bank debates whether to run a full interruption test. Ezequiel, the CRO, sets conditions. Under which circumstances is it MOST justified?
- AAfter lesser tests pass
- BDuring peak periods for realism
- CWhen a regulator suggests it
- DAs a new plan's first test
Show the answer
Correct answer: A. Full interruption is the last step of a mature test program.
- A. Correct. After less disruptive tests succeed, when high assurance is needed and risks are managed with approval.
- B. Incorrect. Peak periods add realism but maximize the harm if the test fails; full interruption tests are scheduled when the impact would be lowest.
- C. Incorrect. Regulatory interest may prompt testing, but the risk is still justified only once lesser tests have shown the plan works.
- D. Incorrect. A new plan should start with low-risk tests such as tabletop and simulation; a full interruption is the last step, not the first.