CISSP subtopic 7.12, Domain 77.12 Test Disaster Recovery Plan (DRP)

This subtopic belongs to Domain 7, "Security Operations", which weighs 13% of the exam. Our bank holds 12 questions on it, split by difficulty as follows.

Theory in the Official Study Guide (10th ed.): chapter 18.

What gets asked on this subtopic

Concepts and situations that appear in our questions for this objective. The exam nearly always frames them as cases where you must decide.

  • Read-through test
  • Full interruption risk
  • Walkthrough vs read-through
  • Test communications
  • Simulation exercise
  • Informing regulators
  • Parallel test isolation
  • Abort criteria
  • Justifying full interruption
  • Measuring test success
  • Unannounced exercises
  • DR testing program

Sample question

Domain 7/7.12 Test Disaster Recovery Plan (DRP)

A regional bank debates whether to run a full interruption test. Ezequiel, the CRO, sets conditions. Under which circumstances is it MOST justified?

  1. AAfter lesser tests pass
  2. BDuring peak periods for realism
  3. CWhen a regulator suggests it
  4. DAs a new plan's first test
Show the answer

Correct answer: A. Full interruption is the last step of a mature test program.

  • A. Correct. After less disruptive tests succeed, when high assurance is needed and risks are managed with approval.
  • B. Incorrect. Peak periods add realism but maximize the harm if the test fails; full interruption tests are scheduled when the impact would be lowest.
  • C. Incorrect. Regulatory interest may prompt testing, but the risk is still justified only once lesser tests have shown the plan works.
  • D. Incorrect. A new plan should start with low-risk tests such as tabletop and simulation; a full interruption is the last step, not the first.