This subtopic belongs to Domain 7, "Security Operations", which weighs 13% of the exam. Our bank holds 19 questions on it, split by difficulty as follows.
Very easy2
Easy5
Medium7
Hard3
Expert2
Theory in the Official Study Guide (10th ed.): chapter 18.
What gets asked on this subtopic
Concepts and situations that appear in our questions for this objective. The exam nearly always frames them as cases where you must decide.
Alternate processing sites
Backup types and restoration
RAID 1
Warm site
Incremental backups
3-2-1 backup rule
Hot site
Mutual assistance agreements
Cloud backup considerations
Active-active vs active-passive
QoS for critical traffic
Power resilience
Recovery site distance
Cloud as recovery site
RAID is not backup
Snapshots vs backups
Resource capacity agreements
Selecting a recovery strategy
Resilience against provider failure
Sample question
This subtopic has no questions in the free test yet; this one is from the same domain.
Domain 7/7.9 Understand and participate in change management processes
A zero-day in a hospital's VPN gateway is being actively exploited, and the vendor has released an emergency patch. The CAB does not meet until next week. Leopoldo, the IT operations manager, decides. What is the BEST course of action?
APatch now; tell the CAB later
BWait for the scheduled CAB
CEmergency change process
DShut the VPN until fully tested
Show the answer
Correct answer: C. Emergency changes are fast but still controlled.
A. Incorrect. Bypassing change control skips approval and rollback planning.
B. Incorrect. Waiting leaves an exploited flaw open for a week.
C. Correct. Expedited approval keeps control and traceability while closing the exposure quickly.
D. Incorrect. A long shutdown disrupts the business unnecessarily.