Domain 3/3.3 Select controls based upon system security requirements
A federal agency's new emergency dispatch system has some moderate weaknesses after its security assessment. It must go live for an urgent mission, and the fixes are planned within 90 days. Under the NIST RMF (Risk Management Framework), which authorization decision is MOST appropriate?
- AAuthorization to operate with a plan of action
- BDenial of authorization until every weakness is fixed
- CInterim authorization that allows testing only
- DCommon control authorization for the hosting platform
Show the answer
Correct answer: A. The question sits in the authorize step of the RMF, after the assessment. The clue "must go live for an urgent mission" weighs against denial, and the moderate findings with a 90-day plan make the risk acceptable with conditions. The authorizing official grants an authorization to operate, records the residual risk and tracks the fixes through a plan of action and milestones, then monitoring continues.
- A. Correct. The official accepts the residual risk for the mission while the plan of action and milestones tracks the 90-day fixes.
- B. Incorrect. Denial suits unacceptable risk; the weaknesses here are moderate and an urgent mission depends on the system going live.
- C. Incorrect. An authorization to test lets the team exercise the system, but the mission needs it in real operation, which testing authority does not allow.
- D. Incorrect. Common control authorization covers controls inherited by many systems; it does not authorize this specific system to operate.